1) measurement of insulation resistance, absorption ratio or polarization index of the stator winding;     2) DC resistance measurement of the stator windings;     3) stator winding leakage current and DC withstand voltage test;     4) AC voltage withstand test of stator and rotor windings;     5) Measurement of insulation resistance and DC resistance of the rotor winding;     6) testing of equipment connected to the excitation circuit of the generator and exciter;     7) Stator core test;     8) Measurement of insulation resistance and shaft voltage of generator and exciter bearings;     9) Rotor winding AC impedance and power loss test;     10) Stator slot coil anti-halation layer to ground potential test;     11) DC voltage measurement is applied to the end of the stator winding of the stator winding;     12) Turbine generator stator winding end natural frequency test;     13) Generator no-load and short-circuit test;     14) Generator temperature rise test;     15) Phase sequence checking and phasing. Conecting Terminals Without Screws Conecting Terminals Without Screws,Cold Pressing Terminals,Low Pressure Cold Shrinkage Terminal,Cold Shrinkage Cable Terminals Taixing Longyi Terminals Co.,Ltd. , https://www.lycopperlugs.com
The synchronous generator test project is a test item for a synchronous generator with a capacity of 0.6 MW or more in the Pre-Regulation (for those below 0.6 MW), including turbo generators and hydro-generators. According to the requirements of the "pre-regulation", the following main test items should be carried out: